To: "Jeffrey Epstein" <jeevacation@gmail.com> Subject: Date: Mon, 16 May 2011 18:38:33 +0000 schedule for the 4th Main pool the building slab will be poured and block going up the pool equipment will be installed and water in pool the retaining walls around cottage will be up the deck will be concrete,ready to lay tile(tile comes after the building is stoned) still on target for 10/3 Flag pole pool the building will be framed in and plastering underway the pool equipment will be in and water in the pool (assumes we get tile selection) the deck will be concrete(tile happens after shelter and plaster) walls will be underway still on target for 9/15 EFTA00665950