From: Daphne eo To: Jeffrey Epstei evacation@gmail.com Ce: ann rodriquez PS Rich on iii Subject: Dome progress - January 23, 2014 Date: Thu, 23 Jan 2014 14:37:46 +0000 Attachments: Dome (1) - Jan_23, 2014.JPG; Dome (2) - Jan_23, 2014.JPG Greetings Mr. Epstein, Attached for your review and comments are dome progress photos. Also for your review is the schedule for the dome completion and installation: Skin of dome will be 75% completed by 1/24, 100% completed by 1/27. Spray painting and sealing of skin to begin 1/27, 100% complete by 2/3. Will dismantle dome for transportation by 2/5 Big N and flatbed will pick up dome on St. John 2/6 or 2/7. Samson crew will reassemble dome on LSJ 2/7 or 2/8. Samson crew and LSJ boom lift will install on roof of Five Palms by 2/10. Final paint touches can be completed on installed dome 2/11 or 2/12. Respectfully submitted, Daphne EFTA00651281